FIDIC设计采购施工(EPC)交钥匙工程合同条件.76
15 Termination by Employer
由雇主终止
15.1 Notice to Correct
通知改正
Ifthe Contractor fails tocarryoutany obligationunderthe Contract,theEmployer may by notice require the Contractor to make good the failure and to remedy it within a specified reasonable time.
如果承包商未能根据合同履行任何义务,雇主可通知承包商,要求其在规定的合理时间内,纠正并补救上述违约行为。