聚力攻坚结硕果 属地建设谱新篇|尼日利亚EDO4项目增项一线115破碎系统顺利带料试车

中材建设有限公司   2026-10-21 10:45:23
广告

640?wx_fmt=png&from=appmsg#imgIndex=0

2026年10月16日,尼日利亚EDO4项目增项一线115破碎系统成功完成带料试车。试车期间,整套系统设备联动运行平稳,标志着115破碎系统正式具备投产条件,成为项目统筹推进增项工程建设的又一重要节点。生产运营全程靠前介入,各岗位紧密联动、积极配合,为本次系统顺利带料试车筑牢运营保障基础。

On October 16, 2026, the 115 crushing system of the Line 115 additional scope under Nigeria's EDO4 Project successfully completed its material commissioning run. Throughout the trial, the entire set of equipment operated smoothly in coordinated linkage, marking that the 115 crushing system is now officially ready for production — another key milestone in the project's integrated push to advance the additional-scope construction. The operations team was engaged front-loaded throughout the process, with all positions working in close coordination and active support, laying a solid operational foundation for the system's successful material commissioning.

115破碎系统是EDO1线石灰石破碎的关键设施,属于EDO4项目部重点增项工程。项目部在高质量推进EDO4项目6000t/d水泥生产线的同时,同步实施115破碎系统、增项煤磨、纸袋厂等多项增项任务。各作业点位相隔约20公里,多点同步施工,现场调度、资源调配压力突出。面对交叉作业繁杂、多方协调难度大等难题,项目团队紧扣履约目标,科学统筹施工组织,紧盯关键线路与核心节点,强化与公司总部、区域公司协同联动,动态调配资源,破解现场各类难题,压缩工序间隙,保障带料试车工作有序推进。

640?wx_fmt=png&from=appmsg#imgIndex=1

本次试车成功,是项目落实全属地化发展战略的生动实践。项目推行全属地化施工模式,属地用工比例达1:10。一方面引入本土施工队伍充实一线,配备属地工程师开展系统化技能培训;另一方面立足现场实践挖掘本土潜力技术人才,择优吸纳为项目部自有员工,组建属地施工班组,建立人才库台账,搭建“引进—培养—选拔—留用—储备”全链条人才梯队。既为本次试车提供坚实人力支撑,也为后续增项煤磨及EDO4项目建设持续输出本土技能人才,践行“建成一个项目、带出一支队伍、留下一批人才”的属地化建设理念。

试车成功既是重要节点,更是全新起点。下一步,

EDO4项目部将严守安全与质量管控,推进数智建造,持续深化属地化建设,高标准推进增项煤磨及后续工程建设,全力推动项目早日达产达标、稳定运行,以优质履约打造海外精品工程,助力公司深耕尼日利亚市场,为建设国际一流绿色低碳解决方案服务商贡献力量。