中建安装国际公司埃及阿拉曼新城项目一次受电成功
Recently, the 22KV main medium-voltage distribution room and auxiliary transformer ofD01 in the Alamein Downtown Towers Project, constructed by CCIEE, successfully achieved energizing on the first attempt. This makes it the first lot among the project’s five packages to complete power transmission, marking a significant acceleration in the commissioning and acceptance phase and laying a solid foundation for project completion.
To ensure the smooth and safe power reception for Lot D01, the project team developed and implemented the "Power Reception Implementation Plan for the Main Medium-Voltage Distribution Room." The plan clarified responsibilities, allocated tasks, and strictly controlled details, enabling the team to complete all pre-power transmission preparations on schedule while maintaining high standards in technical briefings and safety drills. During the commissioning and acceptance process prior to the official power transmission, the project’s professional engineers calmly addressed various design and technical issues raised by the supervisors. The expertise and performance of the CCIEE mechanical and electrical team were highly recognized by all parties, including the consultant engineer, ensuring the timely achievement of the power reception milestone.
The successful power reception for D01 fully demonstrates the strong technical capabilities and efficient execution of the CCIEE team. As the first super-high-rise civil electromechanical project undertaken by the company in the Egyptian market, the team has strived for excellence from design to on-site construction, tackling technical challenges and fostering collaboration. They are now fully advancing subsequent project deliverables, contributing to the cooperation between China and Egypt.
近日,由中建安装国际公司承建的埃及阿拉曼新城超高综合体D01标段22KV主中压配电室及辅助变压器一次受电成功,成为项目五个标段中第一个完成送电的标段,标志着项目调试验收工作进入了“快车道”,为完工奠定了坚实基础。
为确保D01标段顺利安全受电,项目部研究制定了《主中压配电室受电实施方案》,明确责任,落实分工,严控细节,高标准完成各方交底及安全演练,按时完成送电前的各项准备工作。在正式送电前的调试验收过程中,面对监理提出的各项设计与技术问题,项目专业工程师从容应对,中建安装机电团队的专业能力和工作成效得到了监理等各合作方的高度认可,保障了受电节点按时完成。
此次D01楼栋成功受电充分彰显了中建安装团队过硬的技术能力与高效的执行能力,作为进入埃及市场的第一个超高层民用机电项目,从图纸设计到现场施工,从技术攻坚到协同作战,项目团队精益求精,迎难而上,正全力推进后续项目履约,为中埃合作贡献力量。