博兹瓦纳 迪拜 伊拉克 CMEC高层出访三国的缘由与信号
图1:中电工的B电厂
图2:世行对B电厂的后评价
世行总结的6条经验教训
(i) The Bank should ensure that the technical features of investments projects are explicitly addressed in sufficient detail, fully understood, and appropriately reflected in the selection of contractors, the Borrower’s project management structures, and the skills balance of the Bank’s project teams;
(ii) Well-defined and relevant qualification requirements, in conjunction with a thorough due diligence process of examining the qualifications and experience of bidders, are fundamental to selecting a well-qualified Engineering, Procurement, and Construction (EPC) contractor;
(iii) For large and complex investment projects, the capacity needs of the implementing agencies should be carefully assessed by specialized experts with project management experience handling investments of similar scale and technical complexity;
(iv) The skills balance of Bank preparation and supervision teams should closely match the technical, contractual, financial, institutional, and safeguard concerns being addressed in the project;
(v) The project illustrates the importance of project monitoring indicators that can give early warnings of potential problems, so that corrective actions can be taken;
(vi) Large generation investment projects are strategic in nature and their financing and implementation should be driven by a comprehensive analysis of the risks associated with different alternatives for financing and managing such projects, both in the investment and operational phases.